Door Installation Procedures

WALL POSITIONING (90° / 180°)

Betcrete Frames are suitable to be positioned centre, inside or outside flush. It is recommended that all external frames (opening out) be installed with door stops.



 

 
Doorframe position for a 90° Opening Doorframe position for a 180° Opening


 
SETTING UP PROCEDURE
 

A. FOR CAST IN ONE 8/2100 & 9/2100 & 13/2100 DOORFRAMES


 

  • Ensure doorframe is in position ( Square and plump)
  • Use Temporary timber supports (supplied by Builder) and (refundable) Templates (as per illustration)
  • After brickwork is dry, remove support and templates.


 

B. FOR 17/2100 DOORFRAMES


 

  • Place applicable (Refundable) jig within door frame. Clamp styles onto jig supplied with g-clamps.
  • Adjust T-stay until plumb in all directions.
  • Place transom (top piece) in position and align inside rebate on door side.
  • Bend out lugs and proceed with brickwork, filling mortar between frame and brickwork.
  • The reusable jigs must be kept in position until brickwork above the transom is dry.

ALLOW FOR SCREET BY WEDGING FROM OUR JIG



 

CROSS SECTION DIAGRAM