Allowable Load Tables

0,8 mm Thick
1,0 mm Thick
1,2 mm Thick

 

Factored Load Tables

0,8 mm Thick
1,0 mm Thick
1,2 mm Thick
Material:
ASTM446 grade C (galvanised to Z275)

GENERAL

  1. Bond-Dek floor slabs are basically one-way slabs designed to carry uniformly distributed loads. The design does not cater for heavy concentrated loads or moving loads. Where these occur the design should be referred to a civil/structural engineer.
  2. Calculations are generally in accordance with BS5950 : Part 4 1984 (limit states design). Deflection during construction calculated at span/180.
  3. Where the Bond-Dek is not fixed directly to the end supports (e.g. shear studs, hilti nails, etc.) steel closer pieces or transverse straps are required along the ends.
  4. For normal applications of Bond-Dek steel floors, no additional reinforcing other than a light mesh for shrinkage control is required, typically 193 mesh.
  5. For "Fire Applications" of Bond-Dek floors, welded steel mesh reinforcement of 8 mm diameter steel bars at 200 mm spacing in each direction is required, with minimum top cover along supports (typically on top of shear studs). This gives the following ratings for a nominal superimposed load of 2,5 kN/m2 maximum, for spans up to 3,0 m:
    120 minutes - where the thickness of the slab plus any concrete screed is greater than 170 mm, and
    90 minutes - where the thickness of the slab plus any concrete screed is less than 170 mm.

For further information on fire applications contact Brownbuilt. N.B. All tabulated values serve as a guide only for single span conditions, and should be certified and approved by a civil/structural engineer.

ACCESSORIES

The following accessories are available for use with Bond-Dek:
Steel side and end closers, seif-tapping screws, pop rivets, hammer drive screws and flashings made to order.


Section Properties of Steel Decking - Simply Supported Condition

Nominal thickness (mm)

Effective thickness (mm)

Area of steel per metre width or cross section (mm²)

Mass per square metre (kg/m²)

Minimum reduced "Z" per metre width (10³mm³)

Reduced "I" per metre width (1065mm4)

Effective depth of Bond-Dek (mm)

Neutral axis from bottom of Bond-Dek (mm)

0,8

0,76

993

7,8

22,2

0,884

74,76

35,05

1,0

0,96

1254

9,85

30,3

1,170

74,96

36,38

1,2

1,16

1515

11,9

38,7

1,463

75,16

37,37

Installation Procedure

(Read entire procedure before pouring concrete)

Bond-Dek panels act as formwork for wet concrete and reinforcing for the slab. To commence installation the first Bond-Dek panel is placed in the required position with the male interlocking rib pointing in the direction of the laying as per sketch (right). Place the female interlocking rib to the outside. Place the interlocking female rib of the second panel onto the male rib of the first panel at an approximate 45° angle and then lower panel down onto supports locking the side lap together (see sketch, right). repeat for each additional panel.

End Lapping of Sheets

The standard procedure is to lap Bond-Dek and not butt joint it.
To end lap Bond-Dek panels cut back 25 mm on male and female interlocking ribs on the bottom panel then overlap top panel.
Fix with Top Speed screws into beam to ensure lateral stability at supports.

Structural Steelwork

Bond-Dek panels can be conveniently fixed to steel supports with either "Top Speed" screws or shot driven fasteners. One fixing in each pan is required.

Shear Studs

If shear studs are to be used these should be placed in the pan of the panel over a beam. Where panels are end lapped, this lap of 25 mm must be to one side of the beam, allowing for shear stud to be positioned through centre of the beam and fixed through the bottom panel (see sketch, left)

When utilising a closer at the ends of the Bond-Dek panels (see sketch , right), this provides lateral stability without the use of strapping. (Closer to fit snugly over Bond-Dek.)

Concrete or Brick Construction

Before laying any Bond-Dek panels ensure that the top face of the concrete beam or brick wall is level. An uneven top face will result in an excessive amount of concrete in places and therefore possible overloading.
Installation of the Bond-Dek is to simply place the panels onto the  concrete beams or the top of the brick walls. A steel strap is placed across the panels and fixed at each flute (see sketch, left). This is done to ensure lateral stability while casting the slab. When the deck is spanning its maximum, a steel strap should be fixed at mid-span as well as at the ends.

Side Fixing to Supporting Structure

Bend down cut edge of panel and fix with Top Speed or shot driven fastener. Ensure angle * of rib remains the same.
Alternatively a make-up Z-piece 75 mm deep can be fixed to the beam and Bond-Dek.

Fixing to Concrete

Fixing Around Columns

Kerb Flashing

Standard Kerb flashing is secured by riveting the bottom of the deck to the bottom leg of the Kerb flash, and the top of the Bond-Dek rib. Kerb flashings to be a minimum of 1 mm thick.

For "Fire Applications" of Bond-Dek floors, welded steel mesh reinforcement of 8 mm diameter steel bars at 200 mm centres in each direction is required with minimum top cover along supports (typically on top of shear studs).

Pouring Concrete

Pour concrete over load bearing beams. Never exceed a concrete height of 300 mm and avoid load concentrations, i.e. excessive equipment or manpower.

Safe Load Tables

0,8 Thick Bond-dek decking spans during construction (unpropped)
Allowing for a construction load of 1,5 kN/m² plus wet concrete

Slab depth (mm)

140

150

160

170

180

190

200

210

220

230

240

250

Unpropped span (m)

2,7

2,6

2,6

2,5

2,4

2,4

2,3

2,3

2,2

2,2

2,1

2,1

1,0 Thick Bond-dek decking spans during construction (unpropped)
Allowing for a construction load of 1,5 kN/m² plus wet concrete

Slab depth (mm)

140

150

160

170

180

190

200

210

220

230

240

250

Unpropped span (m)

3,2

3,1

3,0

2,9

2,8

2,8

2,7

2,7

2,6

2,6

2,5

2,5

1,2 Thick Bond-dek decking spans during construction (unpropped)
Allowing for a construction load of 1,5 kN/m² plus wet concrete

Slab depth (mm)

140

150

160

170

180

190

200

210

220

230

240

250

Unpropped span (m)

3,5

3,4

3,4

3,3

3,2

3,1

3,1

3,0

2,9

2,9

2,8

2,8

! NEVER POUR CONCRETE AT MID-SPAN.